h4l THE VILLAGE construction starts in 2021 The project is divided into 3 phases and will be completed in June 2024. In this section you can see images from the construction site that show the progress of the project.


Site log
h4l THE VILLAGE
h4l THE VILLAGE construction starts in 2021 The project is divided into 3 phases and will be completed in June 2024. In this section you can see images from the construction site that show the progress of the project.
PHASE 1
- February 2023 – construction completion

The construction works of the h4l THE VILLAGE neighborhood were started with the arrangement of the access road.
Access road construction, h4l THE VILLAGE, for those who want more (1)
Previous
Next
Access road construction, h4l THE VILLAGE, for those who want more (1)
Previous
Next
PHASE 2
- September 2023 – construction completion

FAZA 3
- June 2024 – construction completion

PHASE 4
- May 2024 – construction completion
The construction works of PHASE 4 of the h4l THE VILLAGE neighborhood have started.